Services-what-we-do
  • Services-paving-icon Services-paving-icon-hover
  • Services-concrete-icon Services-concrete-icon-hover
  • Services-earthwork-icon Services-earthwork-icon-hover
  • Services-site-design-survey-icon Services-site-design-survey-icon-hover
  • Services-demolition-icon Services-demolition-icon-hover
  • Services-sunguard-a-e-sealing-icon Services-sunguard-a-e-sealing-icon-hover
  • Services-asphalt-repair-icon Services-asphalt-repair-icon-hover
  • Services-crack-filling-icon Services-crack-filling-icon-hover
  • Services-striping-markings-icon Services-striping-markings-icon-hover
  • Services-running-tracks-icon Services-running-tracks-icon-hover
  • Services-other-services-icon Services-other-services-icon-hover

Mesa USD S.H.A.R.P. Focus School

Public Works - Schools

The Project:

Mesa Unified School District was in need of a bus lane skirting the perimeter of their S.H.A.R.P. Focus School with access to both Adobe Street and Sun Valley Boulevard.  With existing utilities playing a factor in the design, Mesa USD needed an experienced asphalt contractor with new construction experience to help engineer the project.

The Ace Solution:

We rough graded and exported over 5,500 cubic yards of dirt to create storm water retention areas that would allow adequate flow off the asphalt surface of the bus lane.  We also reengineered utility trenches to accommodate existing utility lines.  The bus lane required the grading and subgrade preparation of 6,067 sq. ft. for placement and compaction of 6-inch deep aggregate base course and 3-inch deep asphalt surfacing on top.  We also poured over 3,110 linear feet of concrete curb and gutter as well as 100 square feet of sidewalk.

Related Projects: Guadalupe Roadwork Phases I & II, Maricopa High School, 2010 Census

Notable Projects with Customer:  Mendoza Elementary School, Stapley Jr. High School, Redbird Elementary School, Westwood High School, Hendrix Jr. High School, District Maintenance/Operations Center.

Quick Facts/Technical Specs:
Total Area Graded: 6,790 cubic yards
Total Area Paved: 6,067 square yards
Major Concrete Work: 3 ADA compliant ramps with single curbing, 3,114 linear feet of curb and gutter, 100 sq. ft. of sidewalk, 2 scuppers

Ace Asphalt did a tremendous job getting in and completing the project within a week without one complaint from our local citizens.

Mark J., Town of Guadalupe